Construction continues to progress. Below is a construction at-a-glance:*
ADELPHI AREA MIDDLE SCHOOL

Project Executive: Christian Broyles
Past Month’s Accomplishments:
- Demolition of existing building slab and foundations completed.
- Grading of site for building pad and laydown areas completed.
30-Day Look Ahead:
- Pouring of concrete building foundations will continue.
- First slab on grade pour will begin.
- Underslab utilities will continue.
DREW-FREEMAN MIDDLE SCHOOL
Project Executive: Christian Broyles
Past Month’s Accomplishments:
- Phases I and II of existing building demolition completed.
- Stripping of topsoil and grading of building footprint completed
- Filling of north side of building pad in progress.
- Pouring of concrete building foundations underway.
30-Day Look Ahead:
- Installation of onsite haul road/crane pad to begin.
- Pouring of concrete building foundations to continue.
- Rough grading of site and rough under slab electrical and plumbing work to continue.
- Existing building demolition Phase III to continue.
HYATTSVILLE MIDDLE SCHOOL
Project Executive: Arland Knipe
Past Month’s Accomplishments:
- Phase I and II of demolition of existing school completed.
- Phase III of demolition in progress.
- Clearing and grading of new building pad completed.
- Installation of new fence and erosion controls at Oliver Street completed.
- Construction of site access roads in progress.
30-Day Look Ahead:
- Pouring of concrete building foundations will continue.
- First slab on grade pour will begin.
- Demolition of existing building will continue.
- Underslab utilities will continue.
KENMOOR MIDDLE SCHOOL
Project Executive: Christian Broyles
Past Month’s Accomplishments:
- Cutting and hauling-off to establish rough grading at building pad sector 1 completed.
- Temporary construction parking area installed.
- Concrete trade contractor mobilized and first rebar delivery received.
- Filling of remaining area of building pad to prepare for concrete foundations in progress.
- Construction of haul road around building pad underway.
- Pouring of concrete building foundations on south side of building pad in progress.
- Clearing of trees at south side of site in progress.
30-Day Look Ahead:
- Building pad rough grading will be completed.
- Pouring of concrete building foundations will continue.
- Clearing of soils around site and construction of haul road/laydown areas will be completed.
- Installation of under-slab utilities will begin.
- Installation of underground electrical duct bank will be completed.
SOUTHERN AREA K-8 ACADEMY
Project Executive: Arland Knipe
Past Month’s Accomplishments:
- Excavation of sediment trap and clearing of building pad completed.
- Installation of diversion fence, berm, and swale completed.
- Stripping of topsoil from building pad at west side and proof roll of building pad at east side underway.
- Mulching of trees and plant debris in progress.
- Installation of stone for access roads and construction trailer pad in progress.
30-Day Look Ahead:
- Importing of dirt for building pad at east and west sides to begin.
- Pepco installation of service for temporary power to begin.
- Surcharge and settlement of building pad to begin.
WALKER MILL MIDDLE SCHOOL
Project Executive: Christian Broyles
Past Month’s Accomplishments:
- Imported fill for surcharge/settlement at building pad completed.
- Surcharging/settlement building pad and monitoring of plates by geotechnical engineer ongoing.
- Temporary power to construction entrance for security camera and wheel wash station installed.
- Construction of the haul road around building pad and material laydown area is in progress.
30-Day Look Ahead:
- Surcharge will reach final settlement.
- Cutting and filling to bring building pad to subgrade will begin.
- Any necessary undercutting of subgrade will be completed.
*Please note: Construction timeframes shown above are subject to change.
|