Welcome to the 10th issue of PGCPS Blueprint Schools News and Updates!
 For more information about the program, please visit www.pgcpsblueprintschools.com.
Construction Updates

ADELPHI AREA MIDDLE SCHOOL

Project Executive: Christian Broyles

Past Month’s Accomplishments:
  • Building perimeter exterior knee wall framing and MEPF hangers at building sectors 1A and 1B completed.
  • Interior CMU block walls in the kitchen area completed.
  • Interior wall layout building and elevated concrete deck pours at sector 1B completed.
  • Interior CMU block walls in elevator shaft and sector 2G in progress.
  • Site storm water utilities installation in progress.
  • Pouring of concrete stage ramp in progress.
  • Building foundation wall waterproofing and backfill in progress.
30-Day Look Ahead:
  • Installation of hat channel system and interior wall framing in building sectors 1A, 1B, and 2K is ongoing.
  • MEP ceiling rough-in in building sector 1B is ongoing.
  • MEPF hanger installation and roof panel installation in building sectors 1A and 1B to be completed.
  • Interior CMU block walls in building sector 2G to be completed.
  • Exterior brick around the perimeter of the building to be completed.
  • Exterior wall panel installation in building sectors 2K and 2G is ongoing.
  • Installation of the site storm utility to be completed.
DREW-FREEMAN MIDDLE SCHOOL
Project Executive: Christian Broyles
 
Past Month’s Accomplishments:
  • Steel erection in building sector 2K completed.
  • Installation of metal decking in building sector 1B completed.
  • All elevated concrete decks at sector 1 completed.
  • Installation of roof panels in building sector 2G completed.
  • Installation of building perimeter knee wall in building sectors 1A, 1B and 2G in progress.
  • Installation of secondary steel and top and bottom interior wall track in building sectors 1A and 1B in progress.
  • Installation of secondary exterior steel in building sectors 2G and 2K in progress.
  • Rough in overhead MEPF in sectors 1A and 1B in progress.
  • Installation of fireproofing in building sector 1A in progress.
30-Day Look Ahead:
  • Installation of exterior brick in building sector 1A is ongoing.
  • Installation of interior CMU block walls is ongoing.
  • Installation of fireproofing, drywall framing, roof panels, and interior storm/sanitary lines in building sectors 1A and 1B is ongoing.
HYATTSVILLE MIDDLE SCHOOL
Project Executive: Arland Knipe

Past Month’s Accomplishments:
  • Interior CMU block walls at stage completed.
  • Concrete pouring of stage and stairs at gym completed.
  • Primary steel erection at building sector 1B completed.
  • Building perimeter knee wall construction and secondary steel installation at building sector 1A completed.
  • Metal panel roof at building sector 2K completed.
  • Secondary steel installation and building perimeter knee wall construction at building sector 2K in progress.
  • Installation of interior hat channel and MEPF hangers at building sector 2K in progress.
  • Building foundation wall waterproofing and backfill in progress.
  • MEPF Hangers, interior wall construction, and fireproofing at building sector 1A in progress.
  • Storm water utilities at SW corner in progress.
30-Day Look Ahead:
  • Exterior metal wall panel installation at building sector 1A to begin.
  • MEPF hanger installation, interior wall framing, and one-siding with drywall in building sector 1A is ongoing.
  • Installation of HVAC ductwork at 1st floor of building sector 1A to begin.
  • Installation of interior metal stairs to begin.
  • CMU bracing installation at building sector 2G is ongoing.
  • Underground telecom ductbank installation at west side of site is ongoing.
  • Roof parapet framing and blocking to continue.
  • Concrete slab on metal deck pours at floors 2-4 in sector 1B to continue.
KENMOOR MIDDLE SCHOOL
Project Executive: Christian Broyles

Past Month’s Accomplishments:
  • All secondary steel except for the canopy completed.
  • Installation of the roof panels in building sectors 1A, 1B, and 2K completed.
  • Fireproofing on level 1 of building sector 1B completed.
  • MEPF hangers on level 1 of building sectors 1A and 1B and sector 2K completed.
  • Interior CMU block walls in building sector 2K completed.
  • Building perimeter knee wall installation completed.
  • Fireproofing on level 1 of building sector 1A in progress.
  • Interior hat channel and purlin bracing work in building sectors 1B and 2K in progress.
  • Interior MEP rough-in and interior wall framing on level 1 of building sector 1B in progress.
  • Interior CMU block walls in building sector 2G in progress.
  • Exterior brick install at building sector 1B in progress.
  • MEPF hangers on level 2 of building sector 1B in progress.
  • Fireproofing in building sector 1A in progress.
30-Day Look Ahead:
  • Fireproofing of lath system and interior wall framing in building sectors 1A, 1B, and 2K is ongoing.
  • MEP ceiling rough-in in building sector 2K is ongoing.
  • MEPF hangers installation in building sectors 1A and 1B to be completed.
  • Interior CMU block walls and installation of roof panels in building sector 2G to be completed.
  • Installation of hat channel in building sector 1A to be completed.
  • Exterior brick installation to be completed.
  • Installation of exterior wall panels in building sectors 1B and 2K is ongoing.
  • Installation of site sanitary sewer utility to be completed.
SOUTHERN AREA K-8 ACADEMY
Project Executive: Arland Knipe

Past Month’s Accomplishments:
  • Removal of surcharge at 3-story tower completed.
  • Concrete slab on grade at north center area completed.
  • Concrete building foundations at west entrance area completed.
  • Steel erection at SEQ #1 (east area) completed.
  • Steel erection at SEQ #2A (north center area) completed.
  • Sewer line work at Emerald Hill Drive completed.
  • Concrete slab on grade at 4-story tower in progress.
  • Concrete building foundations at 3-story tower in progress.
  • Metal roof decking at SEQ #1 (east area) in progress.
  • Steel erection at SEQ #2B (north center area) in progress.
  • Storm water utility work at south parking area in progress.
30-Day Look Ahead:
  • Steel erection at SEQ #3 (4-story tower) to begin.
  • Concrete slab on grade at 4-story tower to be completed.
  • Installation of metal roof decking at SEQ #2 (north center) to begin.
  • Building perimeter knee wall construction (east) to begin.
  • Interior CMU block wall construction to begin.
  • TPO roofing installation at SEQ #1 to begin.
WALKER MILL MIDDLE SCHOOL
Project Executive: Christian Broyles

Past Month’s Accomplishments:
  • Steel erection and detailing of steel in building sector 1A completed.
  • Secondary steel in building sector 1B completed.
  • Steel erection, detailing, and secondary steel in building sector 2K completed.
  • Concrete slab on grade at building sector 2G completed.
  • Elevated concrete slabs at building sectors 1A and 1B completed.
  • Soil verification nails for retaining wall completed.
  • Building perimeter knee wall installation building sector 1B in progress.
  • Installation of interior MEP hangers at building sectors 1A and 1B in progress.
  • Interior wall layout and installation of roof panels at building sector 1B in progress.
  • Installation of roof purlin framing at building sector 1A in progress.
30-Day Look Ahead:
  • Installation of roof panels at building sector 1B to be completed.
  • Installation of roof panels at building sector 1A to continue.
  • Construction of exterior wall panels at building sectors 1A and 1B to begin.
  • Primary and secondary steel at building sector 2G to be completed.
  • Interior MEP hangers at first floor of sector 1A to be completed.
  • Fireproofing at first floor of building sectors 1A and 1B to begin.
  • Installation of roof panels at building sector 2K to begin.
 

*Please note: Construction timeframes shown above are subject to change.

For questions and inquiries on construction in your neighborhood,
please call (301) 317-6199 or email blueprintschoolsinfo@gilbaneco.com 
Construction Progress Photos
Want to see construction progress of all six school projects? Click HERE to view!
 
Know someone else who would like to receive Blueprint Schools
Program News & Updates
? Tell them to sign up
HERE

For more information about the program, please visit www.pgcpsblueprintschools.com






This email was sent to <<Email Address>>
why did I get this?    unsubscribe from this list    update subscription preferences
Brailsford & Dunlavey · 1140 Connecticut Ave NW Ste 400 · Washington, DC 20036-4014 · USA

Email Marketing Powered by Mailchimp