Welcome to the 14th issue of PGCPS Blueprint Schools News and Updates!
 For more information about the program, please visit www.pgcpsblueprintschools.com.
Construction Updates

ADELPHI MIDDLE SCHOOL

Project Executive: Christian Broyles

Past Month’s Accomplishments:
  • MEPF hangers installation and interior stud wall layout on level 2 of building sector 1A completed.
  • Installation and pouring of concrete stair tread infills at stairs 2 and 3 completed.
  • Spray fireproofing on level 2 of building sector 2B completed.
  • Installation of exterior metal wall panels and MEP above ceiling rough-in in building sector 1B completed.
  • Underground sanitary piping installation at the parking lot area completed.
  • Installation of ceiling metal lath in building sector 2K completed.
  • Installation of the grease interceptor completed.
  • Electrical in wall rough-in, building foundation wall waterproofing, and backfill  in building sector 1B in progress.
  • MEPF hangers installation and interior wall layout on level 2 of building sector 1B in progress.
  • Spray fireproofing ceiling lath in building sector 2K and on level 2 of building sector 1B in progress.
  • MEPF rough-in in the west commons, gym, and on level 2 of building sector 1B in progress.
  • Installation of TPO roofing at the connector in progress.
  • Installation of exterior windows at building sector 1B and the gym in progress.
  • Installation of interior door frames in building sector 1A in progress.
  • Installation of block retaining walls and site underground storm piping in progress.
30-Day Look Ahead:
  • Interior stud wall framing and MEP ceiling rough-in on level 2 of building sector 1B is ongoing.
  • Installation of exterior wall panels on level 2 of building sectors 1A and 1B is ongoing.
  • Installation of the site underground utilities to continue.
  • Detailing of TPO roofing to continue.
  • Installation of exterior windows and interior door frames is ongoing.
  • MEP in-wall rough-in in building sectors 1A and 1B to continue.
DREW-FREEMAN MIDDLE SCHOOL
Project Executive: Christian Broyles
 
Past Month’s Accomplishments:
  • Installation of exterior brick in building sector 1B completed.
  • Installation of exterior wall panels and window framing in building sectors 1A and 1B completed.
  • Installation of underground grease interceptor near building sector 2K completed.
  • Installation of exterior windows and wall blocking in building sectors 1A and 1B in progress.
  • Spray fireproofing of ceiling lath system in building sector 2K in progress.
  • Installation of drywall top out in building sector 1B in progress.
  • One-sided drywall installations in building sector 1A in progress.
  • Installation of Stair 2 in building sector 1 in progress.
30-Day Look Ahead:
  • One-sided drywall installations in sectors 1A and 1B are ongoing.
  • Spray fireproofing of ceiling lath system on level 2 of building sector 1A is ongoing.
  • Exterior window installations in building sector 1A and level 2 of building sector 1B are ongoing.
  • Installation of stairs 1 and 3 is ongoing.
  • Wall blocking installations in building sector 1A and level 2 of building sector 1B are ongoing.
HYATTSVILLE MIDDLE SCHOOL
Project Executive: Arland Knipe

Past Month’s Accomplishments:
  • Exterior metal panel and interior CMU block wall bracing installation at building sector 2G completed.
  • Primary duct bank installation at north side of site completed.
  • Entrance canopy framing and blocking completed
  • Window installation and caulking at building sector 1A completed.
  • In-wall rough-in on level 1 of building sector 1A completed.
  • Drywall framing and top out in the kitchen of building sector 2K completed.
  • Spray fireproofing on level 4 and stair 1 installation at the tower of building sector 1B completed.
  • TPO roofing installation at connector roofs completed.
  • One-siding drywall, sprinkler installation, electrical in wall rough-in, interior stud wall framing, and electrical power distribution on various level in building sector 1A in progress.
  • Installation of exterior metal wall panels at building sector 1B in progress.
  • Telecom cabling installation in building sectors 1A and 1B in progress.
  • Sanitary tie-in at north side of site in progress.
  • Grading of lower parking lot in progress.
30-Day Look Ahead:
  • MEP, sprinkler, and telecom overhead rough-in testing and insulation is ongoing.
  • Installation of exterior metal panels to be completed.
  • Exterior window installation at building sectors 1B and 2G to begin.
  • Grading of bus loop and lower lot to begin.
  • Gas tie-in at north end of site to begin.
  • Wall close-ins and interior door frame installation at level 1 of building sector 1A to begin.
     
KENMOOR MIDDLE SCHOOL
Project Executive: Christian Broyles

Past Month’s Accomplishments:
  • Spray fireproofing, setting of RTU curbs, canopy outriggers, and installation of primary electrical duct bank and secondary duct bank completed.
  • Interior stud wall framing in building sector 2A completed.
  • Overhead ductwork in building sector 2B completed.
  • Mechanical room equipment delivery to site completed.
  • Electrical rough-in in building sector 1B completed.
  • In-wall HVAC controls rough-in in building sector 1 completed.
  • Stair 2 installation completed.
  • Storm line installation from MH 15 to MH 16 completed. 
  • Installation of exterior wall panels at location of canopy outriggers in progress.
  • Overhead duct work at building sector 2A in progress.
  • Electrical room rough-in on building sector 1A in progress.
  • Installation of exterior windows at the north elevation in progress.
  • Chiller piping from pad to building in progress.
  • Sanitary line connection from kitchen to grease interceptor to sanitary in progress.
  • Building gutters and trim at IMP-Roof in progress.
  • Stair 1 installation and completion of all interior stud wall framing in progress.
  • Ductwork in the center section building sector 1 in progress.
  • Sprinkler piping in building sectors 1A and 2B in progress.
30-Day Look Ahead:
  • Wall close-in inspections and hanging of drywall in building sector 1 are ongoing.
  • Overhead MEP rough-in on level 2 of building sector 2 is ongoing.
  • In-wall electrical rough-ins in building sectors 1A and 2B are ongoing.
  • Door frame delivery is expected.
  • Chiller, transformer, and generator pad installation is ongoing.
  • Installation of storm lines MH 24, MH 25, and MH 27 to begin.
  • Stair 3 installation to begin.
  • IMP wall panels and storefront installation to be completed.
COLIN L. POWELL K-8 ACADEMY
Project Executive: Arland Knipe

Past Month’s Accomplishments:
  • Concrete slab on deck and spray fireproofing on various levels of the 4-story tower completed.
  • Steel erection, metal decking, and detailing of the 3-story tower and west entrance completed.
  • Overhead MEP rough-in in building sectors 1 and 2 completed.
  • Interior wall framing in the kitchen completed.
  • Concrete slab on metal deck at the 3-story tower in progress.
  • Overhead MEP rough-in, secondary steel installation, and spray fireproofing on various levels of the 4-story tower in progress.
  • Installation of insulated metal wall panels in building sector 1 in progress.
  • Interior CMU block wall construction at the aux gym and music spaces in progress.
  • Interior wall framing in the Cafeteria in progress.
  • Curb and gutter of the west parking lot in progress.
  • Preparation of the playfields for autumn planting season in progress.
30-Day Look Ahead:
  • Interior stud wall framing in building sector 2 to begin.
  • Concrete slab on metal deck at the 3-story tower is ongoing.
  • Installation of insulated metal wall panels is ongoing. 
  • Spray fireproofing and overhead MEP rough-in in the 4-Story Tower is ongoing.
  • Curb and gutter construction for parking lots and access road areas is ongoing.
WALKER MILL MIDDLE SCHOOL
Project Executive: Christian Broyles

Past Month’s Accomplishments:
  • Interior MEP overhead rough-in in building sector 1A completed.
  • Spray fireproofing and installation of ceiling metal lath building sector 2K completed.
  • Installation of exterior metal wall panels and CMU support steel at building sector 2G completed.
  • Interior stud wall framing and spray fireproofing on level 2 of building sector 1B completed.
  • Ceiling metal lath installation on level 2 of building sector 2A completed.
  • Installation of stair 2 completed.
  • Pouring of concrete stage and installation of water meter vault completed.
  • Interior MEP overhead rough-in on level 2 of building sector 1B in progress.
  • Installation of interior CMU block walls at building Sector 2G in progress.
  • Installation of TPO roofing and windows in building sector 1 in progress.
  • Interior stud wall framing in building sector 2K in progress.
  • One-side drywall installation on level 1 of building sector 1B in progress.
  • Installation of soil nail retaining wall in progress.
30-Day Look Ahead:
  • Spray fireproofing, interior stud wall framing, and overhead MEP rough-in on level 2 of building sector 1A to begin.
  • Installation of underground site utilities throughout the project site is ongoing.
  • Hanging of one side drywall on level 1 of building sector 1A to begin.
  • Installation of  windows in building sector 2 to begin.
  • Installation of door frames in building sector 1 to begin.
  • Installation of soil nail retaining wall to continue.
 

*Please note: Construction timeframes shown above are subject to change.

For questions and inquiries on construction in your neighborhood,
please call (301) 317-6199 or email
blueprintschoolsinfo@gilbaneco.com 
Mentor Protégé Program Update
Over the last three months, Prince George's County Blueprint Schools Mentor Protégé Program held workshops to assist protégés with scaling their businesses with an emphasis on increasing company capacity through the addition of new products and services and pursuing new clients. Program staff worked with these firms on an intimate level, providing business coaching and supportive service recommendations when appropriate.  

The following protégés attended:  
  • Glinda Jackson, Jackson Management Group 
  • Kevin Lisenby, BCS Supply and Services, LLC 
  • Kurjuan Kirkpatrick, Sentel Construction & Remodeling, LLC
  • Jon Hogans, Advanced Custom Builders
  • Dwight Deloatch, H&B Services
  • Emmalyne Head, Southern Belle Cleaner
Know someone else who would like to receive Blueprint Schools
Program News & Updates
? Tell them to sign up
HERE

For more information about the program, please visit www.pgcpsblueprintschools.com






This email was sent to <<Email Address>>
why did I get this?    unsubscribe from this list    update subscription preferences
Brailsford & Dunlavey · 1140 Connecticut Ave NW Ste 400 · Washington, DC 20036-4014 · USA

Email Marketing Powered by Mailchimp