ADELPHI AREA MIDDLE SCHOOL

Project Executive: Christian Broyles
Past Month’s Accomplishments:
- MEPF hangers and interior wall layout and fire proofing in building sector 1B completed.
- Installation of roof panels in building sectors 1A and 1B completed.
- Forming and pouring of concrete stage and ramp completed.
- Exterior wall panels in building sector 2K completed.
- Framing out of interior walls on first floor and ceiling hat channels in building sector 1A completed.
- Underground site storm water infrastructure at parking lot area completed.
- Interior CMU block elevator shaft walls completed.
- Ceiling hat channel installation and MEPF rough-in in sector 1B in progress.
- Site storm water utilities installation in the soccer field in progress.
- Interior CMU block walls in building sector 2G in progress.
- Building foundation wall waterproofing and backfill in progress.
- MEPF hangers and interior wall layout building in level 2 and fireproofing ceiling lath in sectors 1A and 1B in progress.
30-Day Look Ahead:
- Installation of hat channel system in building sectors 1A, 1B, and 2K is ongoing.
- Interior wall framing in building sectors 1B and 2K is ongoing.
- MEP ceiling rough-in in building sector 1B is ongoing.
- Installation of MEPF hangers in level 2 of building sectors 1A and 1B to be completed.
- Interior CMU block walls in building sector 2G to be completed.
- Exterior brick around the perimeter of the building to be completed.
- Installation of exterior wall panels in building sector 2G to continue.
- Installation of site storm utilities to continue.
DREW-FREEMAN MIDDLE SCHOOL

Project Executive: Christian Broyles
Past Month’s Accomplishments:
- Installation of roof panels and fire proofing and framing out of interior walls on first floor in building sector 1A completed.
- Installation of metal decking and secondary exterior steel in building sectors 2G and 2K completed.
- Hanger rough-in overhead MEPF in building sectors 1A and 1B completed.
- Installation of building perimeter knee wall in building sectors 1A, 1B and 2G completed.
- Installation of secondary steel on building sectors 1A and 1B in progress
- Installation of fireproofing in building sectors 1B and 2G in progress.
- Installation of interior CMU block walls in progress.
- Installation of interior wall framing and MEPF in sector 1A in progress.
- Installation of interior storm/sanitary lines in progress.
30-Day Look Ahead:
- Installation of MEPF in first floor and exterior brick in building sectors 1A and 1B is ongoing.
- Installation of fireproofing in building sectors 2G and 2K is ongoing.
- Installation of interior CMU block walls to continue.
- Installation of roof panels in building sector 1B and 2K is ongoing.
HYATTSVILLE MIDDLE SCHOOL

Project Executive: Arland Knipe
Past Month’s Accomplishments:
- Interior CMU block walls and ceiling hat channel installation for fireproofing at sector 2K completed.
- All concrete slab pours on metal deck floors at sector 1B completed.
- Steel for entrance canopy completed.
- Fireproofing at 1st and 2nd floors of building sector 1A completed.
- Metal panel roof at building sector 2G completed.
- Underground telecom duct bank installation at west side of site completed.
- Secondary steel install at building sectors 1B, 2G, and 2K in progress.
- Building perimeter knee wall construction at building sectors 2G and 2K in progress.
- Building foundation wall waterproofing and backfill in progress.
- MEPF hangers and interior wall construction at building sector 1A (floors 1-3) in progress.
- Interior wall framing and one-siding at sector 1A (Floors 1-2) in progress.
- Spray fireproofing at building sector 1A (Floor 3) and 1B (Floor 1) in progress.
- Storm water utilities at south side of building in progress.
- Installation of stair 3 in progress.
- CMU bracing installation at building sector 2G in progress.
- Roof parapet framing and blocking in progress.
30-Day Look Ahead:
- Exterior metal wall panel installation at building sector 2K to begin.
- MEPF hanger installation at building sectors 1A and1B is ongoing.
- Installation of HVAC ductwork at building sector 1A (2nd and 3rd floors) to continue.
- Installation of interior metal stairs (Stair 2) to begin.
- Fireproofing at 1B sector to continue.
- TPO roof installation to begin.
KENMOOR MIDDLE SCHOOL

Project Executive: Christian Broyles
Past Month’s Accomplishments:
- Brick masonry walls and backfill at the perimeter of the building completed.
- Ceiling hat channel and purlin bracing work and ceiling lath installation in 2K
completed.
- Interior wall framing in level 1 of sector 1B completed.
- 70% of interior wall framing in level 1 of sector 1A completed.
- All MEPF hangers on sector 1A and second level of sector 1B completed.
- Fireproofing in sector 1B level 1, Sector 2G completed.
- Fireproofing in Sector 2K in progress.
30-Day Look Ahead:
- Installation of fireproofing lath system in building sectors 1A (level 2), 1B (level2), and 2K is ongoing.
- Interior wall framing in building sectors 1A and 2K is ongoing.
- MEP ceiling and wall rough-in in building sectors 1B (level 2) and 2K is ongoing.
- Interior CMU block walls and installation of the roof panels in building sector 2G to be completed.
- Installation of exterior wall panels in building sectors 1A, 1B, and 2K to continue.
- Installation of site sanitary sewer utility to be completed.
SOUTHERN AREA K-8 ACADEMY

Project Executive: Arland Knipe
Past Month’s Accomplishments:
- Concrete slab on grade at 4-story tower completed.
- Concrete building foundations and under slab utilities at 3-story tower completed.
- Steel erection at building sequence 2B (North Center area), 3A and 3B (4-story tower) completed.
- Metal roof decking at building sequence 2A and 2B completed.
- Secondary steel at building sequence 1 completed.
- Storm utility work along west side of building pad completed.
- Concrete slab on grade at 3-story tower in progress.
- Steel erection and metal decking at the 4-story tower at building sequence 3 in progress.
- Secondary steel at building sequence 2 in progress.
- Exterior knee wall framing and sheathing in progress.
- MEP hangers install in sequence 1 in progress.
30-Day Look Ahead:
- Interior CMU block wall construction to begin.
- TPO roofing installation at building sequence 1 to begin.
- Concrete slab on deck at 4-story tower to begin.
- Steel erection at 3-story tower to begin.
- Stabilization of playfields to be completed.
WALKER MILL MIDDLE SCHOOL

Project Executive: Christian Broyles
Past Month’s Accomplishments:
- Installation of roof panels building and perimeter knee wall installation at building sectors 1B and 2K completed.
- Secondary steel installation in building sector 1A completed.
- Primary and secondary steel installation in building sector 2G completed.
- Fireproofing on first floor of building sector 1B completed.
- Building perimeter knee wall installation in building sectors 1A and 2G in progress.
- Installation of interior MEP overhead rough-in in building sector 1B in progress.
- Interior wall framing at building sector 1B in progress.
- Interior wall layout building, fireproofing, and installation of roof panels at building sector 1A in progress.
- Installation of CMU at building sector 2K and elevator shaft in progress.
30-Day Look Ahead:
- Installation of roof panels at building sector 1A to be completed.
- Installation of roof panels at building sector 2G to be completed.
- Exterior brick walls and installation of ceiling metal lath in building sector 1B to begin.
- Exterior wall panels building sector 1B & 1A to begin.
- Installation of CMU in building sector 2G to begin.
*Please note: Construction timeframes shown above are subject to change.
|