Construction Updates

ADELPHI AREA MIDDLE SCHOOL

Project Executive: Christian Broyles

Past Month’s Accomplishments:
  • Building perimeter knee wall framing and AVB at sector 2K completed.
  • MEPF hangers and interior wall layout sector 1A completed.
  • Structural steel erection in sectors1A and 1B completed.
  • Exterior metal panel deliveries completed.
  • Elevated concrete deck pours at sector 1A completed.
  • Install roof panels at sectors 2K and 2G completed.
  • Metal decking and MEPF elevated concrete decks rough in sector 1B in progress.
  • Interior CMU block walls in sectors 2G and 2K in progress.
  • Forming and pouring of concrete stage ramp in progress.
  • Building foundation wall waterproofing and backfill in progress.
  • Building perimeter exterior brick knee wall sectors 2K and 2G in progress.
30-Day Look Ahead:
  • Building perimeter knee wall framing and AVB at sectors 1A, 1B, and 2G is ongoing.
  • Roof panel install at sectors 1A and 1B is ongoing.
  • MEPF hangers and interior wall layout Sector 1B to continue.
  • Exterior wall metal panel deliveries are ongoing.
  • Elevated concrete deck pours at sector 1B to begin.
  • Site storm water utilities install to begin.
  • Interior CMU block elevator shaft walls to begin.
DREW-FREEMAN MIDDLE SCHOOL
Project Executive: Christian Broyles
 
Past Month’s Accomplishments:
  • Erection of classroom steel in building sector 1B completed.
  • Installation of metal decking in building sector 1A completed.
  • Installation of concrete slabs in building sector 2K completed.
  • Primary steel erection in building sector 2G completed.
  • Installation of building perimeter knee wall at sector 1A in progress.
  • Pouring of elevated concrete decks at sector 1A in progress.
  • Installation of metal decking in building sector 1B in progress.
  • Installation of secondary steel in building sector 2G in progress.
30-Day Look Ahead:
  • Pouring of elevated concrete decks at sector 1A to continue.
  • Installation of perimeter knee wall and secondary steel in building sectors 1A and 1B is ongoing.
  • Steel erection at building sector 2K to continue.
  • Installation of roof panels at sector 2G to continue.
  • Rough in overhead MEPF in sector 1A is ongoing.
 
HYATTSVILLE MIDDLE SCHOOL
Project Executive: Arland Knipe

Past Month’s Accomplishments:
  • Pouring of elevated concrete deck in sector 1A (3rd and 4th Floors) completed.
  • Primary steel erection at sectors 2G and 2K completed.
  • Interior CMU block elevator shaft walls completed.
  • Grading of turf field area completed.
  • Secondary steel install at sector 1A in progress.
  • Primary steel erection in sector 1B in progress.
  • Building perimeter knee wall framing and sheathing at sector 1A in progress.
  • Building foundation wall waterproofing and backfill in progress.
30-Day Look Ahead:
  • Exterior metal panel deliveries to begin.
  • Metal panel roof installation at sectors 2G and 2K is ongoing.
  • Exterior metal wall panel installation to begin.
  • MEPF hanger installation at sector 1A to continue.
  • Interior wall framing and one-siding with drywall at sector 1A is ongoing.
  • Installation of storm water utilities at the SW corner to begin.
 
KENMOOR MIDDLE SCHOOL
Project Executive: Christian Broyles

Past Month’s Accomplishments:
  • Installation of caissons at the south side of the site completed.
  • Primary and secondary steel in sector 2G completed.
  • Secondary steel wall girts and purlins at all building sectors completed.
  • Roof decking and all elevated concrete deck pours completed.
  • Roof panels in Sector 2K competed.
  • Building perimeter knee wall installation in sectors 2k and 1B completed.
  • Installation of MEP hangers in sector 2K and first floor of sector 1B completed.
  • Entrance canopy steel erection in progress.
  • Installation of interior CMU block walls in sector 2K and elevator shaft in progress.
  • Installation of roof panels in sector 1B and spraying of fireproofing on first floor in progress.
  • MEP hanger installation in sector 1A first floor in progress.
  • Roof panels in sector 1B and move to sector 1A roof panel installation in progress.
30-Day Look Ahead:
  • Interior wall layout and framing in sector 1B first floor is ongoing.
  • Interior installation of ceiling hat channel and lath system in sector 2K is ongoing.
  • Exterior waterproofing/AVB on sheathing/exterior brick at sector 2K to continue.
  • Installation of wall panels in sector 2K to continue.
  • Installation of the exterior sanitary sewer system to be completed.
  • Installation of data/electrical duct banks is ongoing.
 
SOUTHERN AREA K-8 ACADEMY
Project Executive: Arland Knipe

Past Month’s Accomplishments:
  • Slab on grade at east area and main gym completed.
  • Removal of surcharge dirt at the SW end of the building pad completed.
  • Mobilization of steel contractor and inspection of crane completed.
  • Monitoring settlement of fill dirt and surcharge dirt on the building pad in progress.
  • Under slab on grade plumbing and electrical at the 4-story tower in progress.
  • Concrete building foundations at west side of 4-story tower in progress.
  • Grading site at greenfield areas in progress.
  • Delivery of primary and secondary structural steel in progress.
30-Day Look Ahead:
  • Steel erection at east area to begin.
  • Steel erection at north center area to begin.
  • Slab on grade at north center area to be completed.
  • Pouring of concrete slab on grade at 4-story tower to begin.
  • Installation of metal roof decking at east area to begin.
 
WALKER MILL MIDDLE SCHOOL
Project Executive: Christian Broyles

Past Month’s Accomplishments:
  • Steel erection and detailing of steel in sector 1B completed.
  • Sector 2K underground MEP and slab on grade concrete pour completed.
  • Concrete building foundations at sector 2G completed.
  • Steel erection in sector 1A in progress.
  • Underground MEP at sector 2G in progress.
  • Prepping for elevated concrete deck pour at sector 1B in progress.
30-Day Look Ahead:
  • Steel erection at sector 2K to begin.
  • Metal deck and detailing at sector 1A to begin.
  • Pouring of elevated concrete deck at sector 1B to begin.
  • Pouring of slab on grade at sector 2G to begin.
  • Secondary steel install at sector 1B to begin.
 

*Please note: Construction timeframes shown above are subject to change.

For questions and inquiries on construction in your neighborhood,
please call (301) 317-6199 or email blueprintschoolsinfo@gilbaneco.com 
Community Investment Spotlight:
Book Drive for Black History Month

In honor of Black History Month, the UJIMA Baltimore ERG, in conjunction with Gilbane Building Company, hosted a book drive. Over 500 books were collected from cooperating Maryland-based Gilbane employees, local subcontractors on project sites, and the UJIMA Baltimore ERG.
 
“Teamwork and sense of community are the essence of what UJIMA stands for, and we are grateful the Maryland Gilbane team helped make this book drive a success!” affirmed Chapter Lead and Project Manager Cedrick Shelton, Jr.
 
Many of the books received were penned by black authors and celebrated black leaders, history, cultural, artistic and political achievements. Approximately 350 children’s books that were collected will be distributed to K-12 public schools throughout Prince George’s County.

The UJIMA ERG is a community of Black/African American employees and advocates at Gilbane who foster an inclusive culture by attracting and supporting professional development, community engagement and providing a voice across the enterprise. The group is named after the third principle of Kwanzaa, UJIMA, and means collective work and responsibility.
Know someone else who would like to receive Blueprint Schools
Program News & Updates
? Tell them to sign up
HERE

For more information about the program, please visit www.pgcpsblueprintschools.com






This email was sent to <<Email Address>>
why did I get this?    unsubscribe from this list    update subscription preferences
Brailsford & Dunlavey · 1140 Connecticut Ave NW Ste 400 · Washington, DC 20036-4014 · USA

Email Marketing Powered by Mailchimp