Welcome to the 13th issue of PGCPS Blueprint Schools News and Updates!
 For more information about the program, please visit www.pgcpsblueprintschools.com.
Construction Updates

ADELPHI MIDDLE SCHOOL

Project Executive: Christian Broyles

Past Month’s Accomplishments:
  • MEPF hangers, interior stud wall layout, and spraying of fireproofing at building sector 2B completed.
  • Installation and pouring of concrete stair tread infills at stair 1 completed.
  • Exterior wall panel installation at building sector 1A completed.
  • Underground sanitary piping installation at parking lot area completed.
  • Ceiling metal lath on level 2 of building sector 1B and building sector 2K completed.
  • MEP above ceiling rough-in and exterior brick installation at building sector 1B completed.
  • Building foundation wall waterproofing and backfill at building sector 1B in progress.
  • MEPF hangers and interior wall layout on level 2 of building sector 1B in progress.
  • Spraying of fireproofing ceiling lath on level 2 of building sectors 1A and 1B in progress.
  • MEPF rough-in installation at building sector 1A Level 2, West Commons, and Gym in progress.
  • Installation of TPO roof at West Commons in progress.
  • Installation of exterior windows and interior door frames at building sector 1A in progress.
  • Electrical in wall rough-in, installation of block retaining walls, and site underground sanitary piping in progress.
30-Day Look Ahead:
  • Interior stud wall framing on level 2 of building sector 1A is ongoing.
  • MEP ceiling rough-in on level 2 of building sector 1B is ongoing.
  • Installation of exterior wall panels at building sector 1B is ongoing.
  • Installation of site underground utilities to continue.
  • Installation of TPO roof to continue.
  • Installation of exterior windows, interior door frames, and electrical in wall rough-in is ongoing.
DREW-FREEMAN MIDDLE SCHOOL
Project Executive: Christian Broyles
 
Past Month’s Accomplishments:
  • Site underground water utility piping to the building completed.
  • Exterior brick laying and drywall top out at main corridors in building Sector 1A completed.
  • Spraying of fireproofing in building sectors 1B and 2G completed.
  • Interior stud wall framing in building sector 1B completed.
  • Construction of interior CMU block walls in building Sector 2G in progress.
  • MEPF overhead rough-in and fire protection rough-in on level 1 in sectors 1A and 1B in progress.
  • Spraying of fireproofing on level 2 in building sectors 1A and 1B in progress.
  • Exterior wall panels in sectors 1A and 1B in progress.
  • Exterior brick in sectors 1B and 2K in progress.
30-Day Look Ahead:
  • Laying of exterior brick at building sector 2K is ongoing.
  • MEPF rough-in on levels 1 and 2 of building sectors 1A and 1B is ongoing.
  • Spraying of fireproofing and interior stud wall framing on level 2 of building sectors 1A and 1B is ongoing.
  • Installation of exterior wall panels in building sectors 2G and 2K is ongoing.
HYATTSVILLE MIDDLE SCHOOL
Project Executive: Arland Knipe

Past Month’s Accomplishments:
  • Building perimeter knee wall construction at building sector 2G completed.
  • Trim out and flashing exterior metal wall panels at building sectors 1A and 2K completed.
  • Electrical overhead rough-in on level 1 of building sector 1A completed.
  • Interior stud wall framing and top out drywall at level 3 of building sector 1A and levels 1 and 2 of building sector 1B completed.
  • Spraying of fireproofing at levels 2 and 3 of building sector 1B completed.
  • Installation of MEP ceiling hangers and overhead rough-in at level 1 of building sector 1B completed.
  • Roof parapet framing and blocking completed.
  • Stair 2 installation in building sector 1A tower completed.
  • Secondary steel installation and perimeter knee wall construction at building sector 1B in progress.
  • Exterior metal wall panels and interior CMU block wall bracing installation at building at sector 2G in progress.
  • Sprinkler installation at level 1 and Electrical overhead rough-in in levels 1 - 3 of building sector 1A in progress.
  • Interior stud wall framing and one-siding drywall on levels 1- 3 of building sector 1B in progress.
  • Spraying of fireproofing on level 4 and window installation at all levels of building sector 1A in progress.
  • Installation of MEP ceiling hangers and interior stud wall framing on level 1 of building sector 1B in progress.
  • Site underground storm water and water line utilities at south side of building in progress.
  • Stair 1 installation at building sector 1B tower in progress.
  • Grading of lower parking lot at SW corner of site in progress.
30-Day Look Ahead:
  • Exterior metal wall panel installation at building sector 1B to begin.
  • MEP overhead rough-in, testing, and insulation is ongoing.
  • Sprinkler installation at building sector 1A tower in ongoing.
  • Overhead HVAC ductwork installation at building sector 1A and 1B is ongoing.
  • Spraying of fireproofing at level 4 of building sectors 1Aand 1B to continue.
  • TPO roofing installation at building sector 1 and 2 connectors to continue.
  • Secondary steel installation at  building sector 1B tower to continue.
  • Interior door frame Installation at level 1 of building sector 1A to begin.
  • Exterior window installation at building sectors 2K and 2G to begin.
KENMOOR MIDDLE SCHOOL
Project Executive: Christian Broyles

Past Month’s Accomplishments:
  • Spraying of fireproofing in building center and sector 2B completed.
  • Interior stud wall framing in building sector 2B completed.
  • Interior CMU block walls completed
  • Storefront on south and east elevation of building completed.
  • Retaining wall #1, grease interceptor, and TPO roofing installation completed.
  • Installation of exterior wall panels in progress.
  • Overhead and in-wall MEP rough-in in building sectors 2K and 2B in progress.
  • Mechanical room overhead rough-ins and electrical room rough-ins in progress.
  • Exterior windows and rooftop equipment curb installation in progress.
  • Installation of MEP ceiling hangers in building sector 2G in progress.
  • Site underground sanitary and storm piping in progress.
30-Day Look Ahead:
  • Interior stud wall framing on level 2 of building sector 2A is ongoing.
  • Delivery of electrical switchboards to be completed.
  • Overhead MEP rough-in on level 2 of building sector 2A to begin.
  • In-wall electrical rough-in is ongoing and in-wall close-in inspection and hanging drywall to begin.
  • Door frame delivery to be completed.
  • Chiller, transformer, and generator pad installation to begin. 
  • Interior stair deliveries and installation is ongoing.
COLIN L. POWELL K-8 ACADEMY
Project Executive: Arland Knipe

Past Month’s Accomplishments:
  • Concrete slab on deck on level 2 of the 4-story tower completed.
  • Metal decking and detailing level 2 and the roof of the 4-story tower completed.
  • Roofing and MEP ceiling hangers at building sequence 2 completed.
  • Interior CMU block wall construction at the main gym and stage completed.
  • Overhead MEP rough-in at building sequence 1 completed.
  • Site retaining wall completed.
  • Concrete slab on metal deck on level 3 of the 4-story tower in progress.
  • Structural steel and metal decking and detailing of the 3-story tower in progress.
  • Secondary steel installation at the 4-story tower in progress.
  • Spraying of fireproofing on level 1 of building sequence 3 in progress.
  • Overhead MEP rough-in in building sequence 2 in progress.
  • Interior CMU block wall construction at the auxiliary gym and music spaces in progress.
30-Day Look Ahead:
  • Underground storm water pipe installation along Swan Creek Road to begin.
  • Interior stud wall framing in building sequence 1 to begin. 
  • Concrete slab on metal deck pouring at level 4 of the 4-story tower to begin.
  • Installation of exterior wall paneling to begin.
  • Overhead MEP rough-in at level 1 of the 4-story tower to begin. 
  • Secondary steel framing at the 4-story tower to be completed.
WALKER MILL MIDDLE SCHOOL
Project Executive: Christian Broyles

Past Month’s Accomplishments:
  • Spraying of fireproofing on level 1 of building sector 1A completed.
  • Interior stud wall framing at building sector 1A completed.
  • Laying of exterior brick at building sectors 1A and 2G completed.
  • Ceiling metal lath installation on level 2 of building sector 1B completed.
  • Installation of Washington Suburban Sanitary Commission (WSSC) water main division valve on Karen Blvd. completed.
  • Interior CMU block walls in building sector 2K completed.
  • Interior MEP overhead rough-in at building sector 1A in progress.
  • TPO roofing installation in building sector 1 in progress.
  • Spraying of fireproofing and interior stud wall framing on second floor of building sector 1B in progress.
  • Installation of interior CMU block walls and exterior wall panels at building Sector 2G in progress.
  • Installation of ceiling metal lath in building sector 2K in progress.
30-Day Look Ahead:
  • Installation of metal ceiling lath at building sector 1A is ongoing.
  • MEP overhead rough-in on level 2 of building sector 1B is ongoing.
  • TPO roof installation at building sector 2 is ongoing.
  • Underground site utilities throughout the project site to begin.
  • Construction of site retaining wall installation to begin.
 

*Please note: Construction timeframes shown above are subject to change.

For questions and inquiries on construction in your neighborhood,
please call (301) 317-6199 or email
blueprintschoolsinfo@gilbaneco.com 
Know someone else who would like to receive Blueprint Schools
Program News & Updates
? Tell them to sign up
HERE

For more information about the program, please visit www.pgcpsblueprintschools.com






This email was sent to <<Email Address>>
why did I get this?    unsubscribe from this list    update subscription preferences
Brailsford & Dunlavey · 1140 Connecticut Ave NW Ste 400 · Washington, DC 20036-4014 · USA

Email Marketing Powered by Mailchimp