ADELPHI MIDDLE SCHOOL

Project Executive: Christian Broyles
Past Month’s Accomplishments:
- MEPF hangers, interior stud wall layout, and spraying of fireproofing at building sector 2B completed.
- Installation and pouring of concrete stair tread infills at stair 1 completed.
- Exterior wall panel installation at building sector 1A completed.
- Underground sanitary piping installation at parking lot area completed.
- Ceiling metal lath on level 2 of building sector 1B and building sector 2K completed.
- MEP above ceiling rough-in and exterior brick installation at building sector 1B completed.
- Building foundation wall waterproofing and backfill at building sector 1B in progress.
- MEPF hangers and interior wall layout on level 2 of building sector 1B in progress.
- Spraying of fireproofing ceiling lath on level 2 of building sectors 1A and 1B in progress.
- MEPF rough-in installation at building sector 1A Level 2, West Commons, and Gym in progress.
- Installation of TPO roof at West Commons in progress.
- Installation of exterior windows and interior door frames at building sector 1A in progress.
- Electrical in wall rough-in, installation of block retaining walls, and site underground sanitary piping in progress.
30-Day Look Ahead:
- Interior stud wall framing on level 2 of building sector 1A is ongoing.
- MEP ceiling rough-in on level 2 of building sector 1B is ongoing.
- Installation of exterior wall panels at building sector 1B is ongoing.
- Installation of site underground utilities to continue.
- Installation of TPO roof to continue.
- Installation of exterior windows, interior door frames, and electrical in wall rough-in is ongoing.
DREW-FREEMAN MIDDLE SCHOOL

Project Executive: Christian Broyles
Past Month’s Accomplishments:
- Site underground water utility piping to the building completed.
- Exterior brick laying and drywall top out at main corridors in building Sector 1A completed.
- Spraying of fireproofing in building sectors 1B and 2G completed.
- Interior stud wall framing in building sector 1B completed.
- Construction of interior CMU block walls in building Sector 2G in progress.
- MEPF overhead rough-in and fire protection rough-in on level 1 in sectors 1A and 1B in progress.
- Spraying of fireproofing on level 2 in building sectors 1A and 1B in progress.
- Exterior wall panels in sectors 1A and 1B in progress.
- Exterior brick in sectors 1B and 2K in progress.
30-Day Look Ahead:
- Laying of exterior brick at building sector 2K is ongoing.
- MEPF rough-in on levels 1 and 2 of building sectors 1A and 1B is ongoing.
- Spraying of fireproofing and interior stud wall framing on level 2 of building sectors 1A and 1B is ongoing.
- Installation of exterior wall panels in building sectors 2G and 2K is ongoing.
HYATTSVILLE MIDDLE SCHOOL

Project Executive: Arland Knipe
Past Month’s Accomplishments:
- Building perimeter knee wall construction at building sector 2G completed.
- Trim out and flashing exterior metal wall panels at building sectors 1A and 2K completed.
- Electrical overhead rough-in on level 1 of building sector 1A completed.
- Interior stud wall framing and top out drywall at level 3 of building sector 1A and levels 1 and 2 of building sector 1B completed.
- Spraying of fireproofing at levels 2 and 3 of building sector 1B completed.
- Installation of MEP ceiling hangers and overhead rough-in at level 1 of building sector 1B completed.
- Roof parapet framing and blocking completed.
- Stair 2 installation in building sector 1A tower completed.
- Secondary steel installation and perimeter knee wall construction at building sector 1B in progress.
- Exterior metal wall panels and interior CMU block wall bracing installation at building at sector 2G in progress.
- Sprinkler installation at level 1 and Electrical overhead rough-in in levels 1 - 3 of building sector 1A in progress.
- Interior stud wall framing and one-siding drywall on levels 1- 3 of building sector 1B in progress.
- Spraying of fireproofing on level 4 and window installation at all levels of building sector 1A in progress.
- Installation of MEP ceiling hangers and interior stud wall framing on level 1 of building sector 1B in progress.
- Site underground storm water and water line utilities at south side of building in progress.
- Stair 1 installation at building sector 1B tower in progress.
- Grading of lower parking lot at SW corner of site in progress.
30-Day Look Ahead:
- Exterior metal wall panel installation at building sector 1B to begin.
- MEP overhead rough-in, testing, and insulation is ongoing.
- Sprinkler installation at building sector 1A tower in ongoing.
- Overhead HVAC ductwork installation at building sector 1A and 1B is ongoing.
- Spraying of fireproofing at level 4 of building sectors 1Aand 1B to continue.
- TPO roofing installation at building sector 1 and 2 connectors to continue.
- Secondary steel installation at building sector 1B tower to continue.
- Interior door frame Installation at level 1 of building sector 1A to begin.
- Exterior window installation at building sectors 2K and 2G to begin.
KENMOOR MIDDLE SCHOOL

Project Executive: Christian Broyles
Past Month’s Accomplishments:
- Spraying of fireproofing in building center and sector 2B completed.
- Interior stud wall framing in building sector 2B completed.
- Interior CMU block walls completed
- Storefront on south and east elevation of building completed.
- Retaining wall #1, grease interceptor, and TPO roofing installation completed.
- Installation of exterior wall panels in progress.
- Overhead and in-wall MEP rough-in in building sectors 2K and 2B in progress.
- Mechanical room overhead rough-ins and electrical room rough-ins in progress.
- Exterior windows and rooftop equipment curb installation in progress.
- Installation of MEP ceiling hangers in building sector 2G in progress.
- Site underground sanitary and storm piping in progress.
30-Day Look Ahead:
- Interior stud wall framing on level 2 of building sector 2A is ongoing.
- Delivery of electrical switchboards to be completed.
- Overhead MEP rough-in on level 2 of building sector 2A to begin.
- In-wall electrical rough-in is ongoing and in-wall close-in inspection and hanging drywall to begin.
- Door frame delivery to be completed.
- Chiller, transformer, and generator pad installation to begin.
- Interior stair deliveries and installation is ongoing.
COLIN L. POWELL K-8 ACADEMY

Project Executive: Arland Knipe
Past Month’s Accomplishments:
- Concrete slab on deck on level 2 of the 4-story tower completed.
- Metal decking and detailing level 2 and the roof of the 4-story tower completed.
- Roofing and MEP ceiling hangers at building sequence 2 completed.
- Interior CMU block wall construction at the main gym and stage completed.
- Overhead MEP rough-in at building sequence 1 completed.
- Site retaining wall completed.
- Concrete slab on metal deck on level 3 of the 4-story tower in progress.
- Structural steel and metal decking and detailing of the 3-story tower in progress.
- Secondary steel installation at the 4-story tower in progress.
- Spraying of fireproofing on level 1 of building sequence 3 in progress.
- Overhead MEP rough-in in building sequence 2 in progress.
- Interior CMU block wall construction at the auxiliary gym and music spaces in progress.
30-Day Look Ahead:
- Underground storm water pipe installation along Swan Creek Road to begin.
- Interior stud wall framing in building sequence 1 to begin.
- Concrete slab on metal deck pouring at level 4 of the 4-story tower to begin.
- Installation of exterior wall paneling to begin.
- Overhead MEP rough-in at level 1 of the 4-story tower to begin.
- Secondary steel framing at the 4-story tower to be completed.
WALKER MILL MIDDLE SCHOOL

Project Executive: Christian Broyles
Past Month’s Accomplishments:
- Spraying of fireproofing on level 1 of building sector 1A completed.
- Interior stud wall framing at building sector 1A completed.
- Laying of exterior brick at building sectors 1A and 2G completed.
- Ceiling metal lath installation on level 2 of building sector 1B completed.
- Installation of Washington Suburban Sanitary Commission (WSSC) water main division valve on Karen Blvd. completed.
- Interior CMU block walls in building sector 2K completed.
- Interior MEP overhead rough-in at building sector 1A in progress.
- TPO roofing installation in building sector 1 in progress.
- Spraying of fireproofing and interior stud wall framing on second floor of building sector 1B in progress.
- Installation of interior CMU block walls and exterior wall panels at building Sector 2G in progress.
- Installation of ceiling metal lath in building sector 2K in progress.
30-Day Look Ahead:
- Installation of metal ceiling lath at building sector 1A is ongoing.
- MEP overhead rough-in on level 2 of building sector 1B is ongoing.
- TPO roof installation at building sector 2 is ongoing.
- Underground site utilities throughout the project site to begin.
- Construction of site retaining wall installation to begin.
*Please note: Construction timeframes shown above are subject to change.
|