Construction continues to progress. Below is a construction at-a-glance:*
ADELPHI AREA MIDDLE SCHOOL

Project Executive: Christian Broyles
Past Month’s Accomplishments:
- Installation of sediment ponds on site and tree clearing completed.
- Demolition of existing school completed.
- Demolition of existing building slab and foundations underway.
- Grading of the site for building pad and laydown areas in progress.
30-Day Look Ahead:
- Laying of concrete building foundations to begin.
- Under slab plumbing and electrical work to begin.
DREW-FREEMAN MIDDLE SCHOOL
Project Executive: Christian Broyles
Past Month’s Accomplishments:
- Interior building abatement and demolition completed.
- Erosion and sediment control measures throughout project site completed.
- Stripping of topsoil, rough grading of site, and existing building demolition in progress.
30-Day Look Ahead:
- Rough grading of the site and existing building demolition to continue.
- Installation of onsite haul road/crane pad.
- Laying of concrete building foundations to begin.
HYATTSVILLE MIDDLE SCHOOL
Project Executive: Arland Knipe
Past Month’s Accomplishments:
- Erosion and sediment control measures at site perimeter and construction entrances completed.
- Interior abatement at existing school completed.
- Demolition of the existing school in progress.
- Clearing and grading for the building pad ongoing.
30-Day Look Ahead:
- Laying of concrete building foundations to begin.
- Under slab plumbing and electrical work to begin.
KENMOOR MIDDLE SCHOOL
Project Executive: Christian Broyles
Past Month’s Accomplishments:
- Erosion and sediment control measures at perimeter and onsite completed.
- Clearing & grading of building pad underway.
- Installation of temporary site roads and a worker parking area in progress.
30-Day Look Ahead:
- Importing and exporting of dirt for the building pad to be completed
- Laying of concrete building foundations to begin.
- Under slab plumbing and electrical work to begin.
SOUTHERN AREA K-8 ACACEMY
Project Executive: Arland Knipe
Past Month’s Accomplishments:
- Clearing and erosion and sediment control measure installation at the site perimeter completed.
- Installation of temporary site electrical power completed.
- Mass clearing of the site and the hauling off of fallen trees and debris in progress.
30-Day Look Ahead:
- Excavation of sediment trap.
- Completion of the mass clearing of site.
- Completion of the hauling of fallen trees.
- Importing of dirt for building pad to begin.
WALKER MILL MIDDLE SCHOOL
Project Executive: Christian Broyles
Past Month’s Accomplishments:
- Erosion and sediment control measures installed at the site perimeter.
- Construction of site sediment trap completed.
- Stripping of topsoil and rough grading of site in progress.
30-Day Look Ahead:
- Stripping of topsoil to be completed.
- Importing of dirt for building pad to begin.
- Tree removal to begin.
*Please note: Construction timeframes shown above are subject to change.
|