Welcome to the third issue of PGCPS Blueprint Schools News and Updates! We are excited to share construction updates and news about our Community Asset Program. Stay tuned for more great issues to come!

 For more information about the program, please visit
www.pgcpsblueprintschools.org.
DESIGN UPDATES
In August, PGCPS issued a Notice to Proceed, the advancement of all six Blueprint School projects from Design Development (or 65% Construction Documents) to 95% Construction Documents, which are scheduled to be issued at the end of December 2021. Advanced designs for specialized spaces such as STEAM and science labs and media centers progressed. Additionally, exterior colors, inspired by nature, were explored and selected for each of the six schools.
CONSTRUCTION UPDATES

Construction continues to progress. Below is a construction at-a-glance:*


ADELPHI AREA MIDDLE SCHOOL

Project Executive: Christian Broyles

Past Month’s Accomplishments:
  • Installation of sediment ponds on site and tree clearing completed.
  • Demolition of existing school completed.
  • Demolition of existing building slab and foundations underway.
  • Grading of the site for building pad and laydown areas in progress.
30-Day Look Ahead:
  • Laying of concrete building foundations to begin.
  • Under slab plumbing and electrical work to begin.

DREW-FREEMAN MIDDLE SCHOOL

Project Executive: Christian Broyles

Past Month’s Accomplishments:
  • Interior building abatement and demolition completed.
  • Erosion and sediment control measures throughout project site completed.
  • Stripping of topsoil, rough grading of site, and existing building demolition in progress.
30-Day Look Ahead:
  • Rough grading of the site and existing building demolition to continue.
  • Installation of onsite haul road/crane pad. 
  • Laying of concrete building foundations to begin.

HYATTSVILLE MIDDLE SCHOOL

Project Executive: Arland Knipe

Past Month’s Accomplishments:
  • Erosion and sediment control measures at site perimeter and construction entrances completed.
  • Interior abatement at existing school completed.
  • Demolition of the existing school in progress.
  • Clearing and grading for the building pad ongoing.
30-Day Look Ahead:
  • Laying of concrete building foundations to begin.
  • Under slab plumbing and electrical work to begin.

KENMOOR MIDDLE SCHOOL

Project Executive: Christian Broyles

Past Month’s Accomplishments:
  • Erosion and sediment control measures at perimeter and onsite completed.
  • Clearing & grading of building pad underway.
  • Installation of temporary site roads and a worker parking area in progress. 
30-Day Look Ahead:
  • Importing and exporting of dirt for the building pad to be completed
  • Laying of concrete building foundations to begin.
  • Under slab plumbing and electrical work to begin.

SOUTHERN AREA K-8 ACACEMY

Project Executive: Arland Knipe

Past Month’s Accomplishments:
  • Clearing and erosion and sediment control measure installation at the site perimeter completed.
  • Installation of temporary site electrical power completed.
  • Mass clearing of the site and the hauling off of fallen trees and debris in progress.
30-Day Look Ahead:
  • Excavation of sediment trap. 
  • Completion of the mass clearing of site. 
  • Completion of the hauling of fallen trees. 
  • Importing of dirt for building pad to begin.

WALKER MILL MIDDLE SCHOOL

Project Executive: Christian Broyles

Past Month’s Accomplishments:
  • Erosion and sediment control measures installed at the site perimeter.
  • Construction of site sediment trap completed.
  • Stripping of topsoil and rough grading of site in progress.
30-Day Look Ahead:
  • Stripping of topsoil to be completed.
  • Importing of dirt for building pad to begin.
  • Tree removal to begin.

*Please note: Construction timeframes shown above are subject to change.

For questions and inquiries on construction in your neighborhood,
please call (301) 317-6199 or email blueprintschoolsinfo@gilbaneco.com 
COMMUNITY INVESTMENT
Learn about the Community Asset Program!
As part of the Blueprint Schools’ commitment to ensuring that each school reflects the dynamism and character of its surrounding community, the Blueprint Schools Community Asset Program (CAP) has been launched. CAP is an innovative and collaborative initiative developed to provide each school with personalized and unique assets.  

The CAP program will include six community investment projects (one per school) – led by the Project Planning Committees (PPCs)* and community stakeholders of each Blueprint School. Each CAP project will have its own share of funding from the project budget that can be supplemented by grants or other funding sources that may be available. Potential examples of these projects could be outdoor fitness equipment, public art, greenhouses, unique wayfinding signage, and/or community programming.  


Over the coming months, Blueprint Schools will work with the PPCs to shepherd these projects from ideas to implementation, thus creating dynamic enhancements for each of these state-of-the-art educational environments. 
Know someone else who would like to receive Blueprint Schools
Program News & Updates
? Tell them to sign up
HERE

For more information about the program, please visit www.pgcpsblueprintschools.com






This email was sent to <<Email Address>>
why did I get this?    unsubscribe from this list    update subscription preferences
Brailsford & Dunlavey · 1140 Connecticut Ave NW Ste 400 · Washington, DC 20036-4014 · USA

Email Marketing Powered by Mailchimp