Welcome to the eighth issue of PGCPS Blueprint Schools News and Updates!
 For more information about the program, please visit
www.pgcpsblueprintschools.com.
Construction Updates

ADELPHI AREA MIDDLE SCHOOL

Project Executive: Christian Broyles

Past Month’s Accomplishments:
  • All underslab plumbing and electrical completed.
  • All concrete slabs on grade completed.
  • Erection of steel in the Kitchen and Gym sectors completed.
  • Erection of classroom steel in building sectors 1A and 1B in progress.
  • Form/pour stage ramp/slab and foundation wall damp-roofing and backfill in progress.
30-Day Look Ahead:
  • Building perimeter knee wall framing and AVB at sectors 1A, 2K, and 2G is ongoing.
  • Roof parapet framing for east commons is ongoing.
  • MEP hangers and interior wall layout at sector 1A to begin.
  • Structural steel erection in sectors 1A and 1B to continue.
  • Façade metal panel deliveries to begin.
  • Slab on deck pours at 1A to continue.
 
DREW-FREEMAN MIDDLE SCHOOL
Project Executive: Christian Broyles
 
Past Month’s Accomplishments:
  • Installation of concrete slabs on grade in building sector 2G completed.
  • Installation of concrete building foundations in building sector 2K in progress.
  • Underslab plumbing and electrical in building sector 2K completed.
  • Erection of classroom steel in building sector 1A completed.
  • Erection of classroom steel in building sector 1B in progress.
  • Pouring of concrete foundation walls in building sector 2K in progress.
     
30-Day Look Ahead:
  • Pouring of concrete slabs on grade in building sector 2K to be completed.
  • Knee wall installation in building sectors 1A and 1B is ongoing.
  • Installation of secondary steel in classroom sectors 1A and 1B to continue.
  • Erection of steel in building sector 2G and 2K to continue.
 
HYATTSVILLE MIDDLE SCHOOL
Project Executive: Arland Knipe

Past Month’s Accomplishments:
  • Pouring of sector 1A concrete slab on metal deck (2nd Floor) completed.
  • Steel detailing and secondary steel install at sector 1A in progress.
  • Primary steel erection at 2K in progress.
  • MEP slab rough-in at the sector 1A elevated decks in progress.
  • CMU walls in sector 2G and CMU elevator shaft in progress.
  • Grading turf field in progress.
  • Foundation wall damp-roofing and backfill in progress.
     
30-Day Look Ahead:
  • Building perimeter knee wall framing and AVB at sector 1A is ongoing.
  • Roof parapet framing at sector 1A is ongoing.
  • MEP Hangers and Interior Wall Layout at sector 1A to begin.
  • Structural steel erection in sectors 2K, 2G, and 1B to continue.
  • Façade metal panel deliveries to begin.
  • Concrete slab on deck pours at sector 1A floors 3 and 4 to continue.
 
KENMOOR MIDDLE SCHOOL
Project Executive: Christian Broyles

Past Month’s Accomplishments:
  • Concrete slab on grade in sector 2G and center infill completed.
  • Primary and secondary steel in sector 2K completed.
  • Primary steel in sectors 1A and 1B completed.
  • Pouring of slab on metal deck in sector 1B completed.
  • Secondary steel installation in sectors 1A, 1B, and Infills in progress.
  • Metal decks, MEP prep, and concrete pours in sectors 1A and 1B to continue.
  • Knee wall installation and waterproofing around the perimeter of the building in progress.
     
30-Day Look Ahead:
  • Steel erection of sector 2G and center infill to be completed.
  • Roof Panel Installation and exterior masonry walls in Sector 2K and 1B to begin.
  • Interior layout of critical walls (MEP rooms, bathrooms, corridors) to begin.
  • Main power duct bank run from existing school to new building to begin.
  • MEP hangers and top track in sector 1B first floor to begin.
 
SOUTHERN AREA K-8 ACADEMY
Project Executive: Arland Knipe

Past Month’s Accomplishments:
  • Foundations and elevator pit at 4-story tower completed.
  • Under slab plumbing and electrical at east and north center areas completed.
  • Preparation for slab on grade pour at east area completed.
  • Monitoring settlement of fill dirt and surcharge dirt on the building pad in progress.
  • Grading of site at the green field and playing court areas in progress.
  • Delivery of steel joists and metal decking in progress.
  • Mobilization of steel erector and crane to site in progress.
30-Day Look Ahead:
  • Pouring of concrete slab on grade at east side to begin.
  • Under slab MEP utilities at 4-story tower to begin.
  • Pouring of concrete slab on grade in gym to begin.
  • Erection of structural steel to begin.
 
WALKER MILL MIDDLE SCHOOL
Project Executive: Christian Broyles

Past Month’s Accomplishments:
  • Rough in MEP underground utilities in sector 1A completed.
  • Deliveries of structural steel completed.
  • Pouring of concrete slab on grade in sector 1B completed.
  • Pouring of concrete slab on grade in sector 1A completed.
  • Steel erection in sector 1B in progress.
  • Installation of concrete building foundations and rough in of MEP underground utilities in sector 2K in progress.
  • Installation of concrete building foundations in sector 2G in progress.
30-Day Look Ahead:
  • Detailing of steel in sector 1B to begin.
  • Steel erection in sector 1A to begin.
  • Concrete building foundations in sector 2K to be completed.
  • Pouring of concrete slab on grade in sector 2K to begin.
  • Finish concrete building foundations in sector 2G to be completed.
     

*Please note: Construction timeframes shown above are subject to change.

For questions and inquiries on construction in your neighborhood,
please call (301) 317-6199 or email blueprintschoolsinfo@gilbaneco.com 
Mentor Protégé Program Spotlight: Minority Environmental Solutions and Services

 
Prince George's County Blueprint Schools Mentor Protégé Program provides minority and county-based businesses opportunities to broaden their industry knowledge and skills as well as gain access to work with Gilbane Building Company (GBC).

We are excited to spotlight one of our recent Mentor Protégé graduates, Minority Environmental Solutions and Services (MESS).
 
MESS is a minority- and woman-owned erosion and sediment control company, founded by Donna MP Wilson, Esq., former director of the Prince George’s County Department of Environmental Resources. The MESS team has extensive experience in environmental control, project engineering, and real estate development.
 
After successful completion of the first Mentor Protégé Program cohort, MESS was awarded work by GBC on both Hyattsville Middle and Southern Area Academy projects. Additional work has been awarded to the team through PGCPS Department of Capital Programs, in collaboration with AC Reliable, on the Surrattsville High School project.
 
For more information on MESS, visit their website at https://www.messenvironmental.com.
Know someone else who would like to receive Blueprint Schools
Program News & Updates
? Tell them to sign up
HERE

For more information about the program, please visit www.pgcpsblueprintschools.com






This email was sent to <<Email Address>>
why did I get this?    unsubscribe from this list    update subscription preferences
Brailsford & Dunlavey · 1140 Connecticut Ave NW Ste 400 · Washington, DC 20036-4014 · USA

Email Marketing Powered by Mailchimp